ESCALATION OF PROJECT COSTS IN THE PLANNING PROCESS |
Line |
FTA Report
Date of
Earlier
Estimate |
Cost per Mile in Millions |
Years
Since
Earlier
Estimate |
Earlier
Estimate |
2000 or 1999
Cost per Mile |
%
Change |
Dallas-North Central Extension |
1997 |
$27.77 |
$41.38 |
49.0% |
2 |
San Diego-Mission Valley |
1999 |
$61.19 |
$73.05 |
19.4% |
1 |
Denver-Southeast |
1999 |
$30.25 |
$46.45 |
53.5% |
1 |
Kansas City-Southtown |
1995 |
$32.00 |
$44.23 |
38.2% |
4 |
Minneapolis-Hiawatha |
1999 |
$32.00 |
$47.70 |
49.1% |
1 |
New Jersey; Hudson Bergen Complete |
1996 |
$63.41 |
$104.72 |
65.1% |
3 |
Norfolk |
1995 |
$7.35 |
$28.67 |
289.9% |
4 |
Orange County |
1999 |
$68.57 |
$75.75 |
10.5% |
1 |
Orlando |
1997 |
$35.20 |
$41.10 |
16.8% |
2 |
Phoenix |
1999 |
$30.00 |
$47.78 |
59.3% |
1 |
Portland-North South |
--- |
$98.83 |
$98.83 |
0.0% |
0 |
San Diego-Mid Coast |
1997 |
$22.65 |
$30.76 |
35.8% |
3 |
San Francisco |
1999 |
$79.59 |
$98.83 |
24.2% |
1 |
Average |
54.7% |
1.5 |
Average without Norfolk |
32.4% |
1.8 |
Annual Average Increase in Costs |
29.6% |
  |
Annual Average Increase in Costs without Norfolk |
21.0% |
  |